This project presented several technical hurdles that Garcia had to overcome, such as the need to have the site sufficiently prepared 6 months after project start so that the extruder's production machinery could be installed, tested and operational by the end of the project.
The presence of a river nearby meant that Garcia had to take several environmental precautions, including the need to create a raised platform of approximately 15,000m2 to prevent flooding and the constant need for waste control to ensure that nothing was damaged or polluted.
2023
44 870m2
Fafe
12 months